|
Applied
Technology Offers Solutions For Jacobs Engineering And Flint Hills
Resources ...continued
To ensure that additional compatibility issues would not
surface, D-R asked the OEM to review the original bills of
materials for the two located units and compare them to the unit
supplied to Flint Hills Resources in 1991. The manufacturer was
cooperative with D-R and agreed to review the bills and also
provided a quotation for the nine-inch stroke crankshaft. The
results of the research presented even more of a challenge to D-R’s
Applied Technology group.
"The two frames held by the equipment supplier were
fabricated frames while the two units operated by Flint Hills
Resources were cast frames," Lottes explained. "If this
was not challenge enough, the manufacturer also informed us that
the crankshaft supplied with the Flint Hills Resources’ units
would not fit into the older style fabricated base. In addition,
it had never designed a nine-inch stroke crankshaft for the
11-inch stroke, two-throw, 60,000-pound rod load fabricated
frame."
To keep the project moving, D-R contacted several known 11-inch
stroke, two-throw, 60,000-pound rod load frame owners to determine
if they had any immediate plans to decommission any of their
units. This yielded no results. Having exhausted these possible
solutions, D-R contacted the manufacturer again to determine if it
would be able to manufacture a new frame with running gear.
However, the manufacturer had discontinued this product line in
1996 and closed the plant.
It was decided that the OEM could produce a new frame with
running gear at one of its other plants. However, the estimated
lead-time for the new frame was 34 weeks.
"Considering we would then need to assemble the distance
pieces, cylinders, do all of the tubing, conduit runs and oil
piping, as well as run tests, we were looking at nearly a 45-week
time period to provide the unit to Jacobs," Lottes recalled.
"A new D-R unit could be provided in far less time."
When Flint Hills Resources considered all of the options, it
was determined that the familiarity of working with
"duplicate" equipment, as well as the advantages in
replacement parts, outweighed the reduced lead time factor of a
new unit.
The first order is for D-R to provide Jacobs with one new
two-throw, 60,000-pound rod load frame compressor. The scope of
supply includes a new frame with two new D-R forged steel
cylinders, distance pieces and auxiliaries, including pulsation
vessels, motor, lube oil console, jacket water console, nitrogen
buffer and control panels. This order represents the
"duplicate" unit Flint Hills Resources needed to satisfy
increased demands at its Corpus Christi facility.
The second order encompasses a new motor with drive components
and auxiliaries including pulsation vessels, motor, lube oil
console, jacket water console, nitrogen buffer and control panels
for an existing smaller, single-throw compressor that Flint Hills
Resources has had in storage since 1992. This equipment was
delivered in September 2002.
"The success of this project can be attributed to many
things," Lottes said. "But, what it really comes down to
is the excellent relationship D-R has developed and maintained
with Jacobs Engineering and Flint Hills Resources." 

|