|
Dresser-Rand succeeds With Applied DATUM Technology For Major U.S. Refinery In Record Time
Just over ten years ago,
Dresser-Rand (D-R)
debuted its high-efficiency
DATUM centrifugal
compressors – a technologically
advanced line that
set new standards for the
industry. Their unique
design resulted in superior
product performance, and
reduced cycle time.
Because of its ability to be
applied to upgrade
installed units (even those
of D-R’s competitors),
DATUM technology gave
D-R an opportunity to
assist clients faced with the
challenge of maintaining
the reliability and performance
of their older
compression units. A
decade later, the DATUM
design concept continues
to successfully meet
clients’ equipment performance
needs.
Recently, Dresser-Rand
succeeded in providing
such a client with a
performance upgrade
solution that applied
DATUM technology to
another OEM’s equipment
within a scheduled sevenday
plant shutdown.
A major oil refinery in the
Midwest United States
contained a horizontally
split three-stage refrigeration
compressor that had
been installed by a D-R
competitor in 1965. The
company sought a more
efficient design to lower
the horsepower required
by the current compressor
because the steam
turbine’s existing power
capability was insufficient
during high-ambient
temperature days. They
also wanted the ability to
compress 15 percent more
propylene within the
existing steam turbine
horsepower capability.
The refinery needed a
solution that would address
the change in design and
the greater efficiency
needed, while still being
cost effective and timely.
D-R approached the
client’s management team
with a proposal to revamp
this equipment using a
high-efficiency DATUM
rotor, diaphragms, and
impellers, commonly
referred to as a “bundle.”
Because of Dresser-Rand’s
history with this client, and
a proven track record with
similar projects for other
clients, the company was
confident that D-R could
address the goals of the
revamp. This project,
however, did present some
challenges.
The refinery had several
unique accessibility and
timing issues regarding this
revamp that D-R would
have to work around. The
facility was scheduled for a
plant turn-around, and the
compressor would not be
accessible to D-R until that
time. The plant would be
operational again in seven
days, giving D-R only one
week to complete installation
of the revamp
hardware after the parts
were completed. Because
the unit could not be
shipped before the actual
installation of the DATUM
internals, D-R would not
have early access to all the
dimensional details
required for final machining
of some parts.“ While this
timing is normal for a plant
turn-around, it was unusual
to not have all the dimensions
needed to complete
the manufacturing of the
new compressor internal
components,” explained
Jeff Worst, senior product
design engineer for
Dresser-Rand. “D-R was
missing the required
information to fit the new
bundle into the existing
compressor case.”
Although the refinery’s
management understood
the complexity of the task it
was putting before D-R,
the final fit dimension
would have to wait.
The biggest challenge was
trying to design parts
without benefit of original
design drawings. Dresser-
Rand was required to
develop the internals with
very little information. D-R
workers realized they
could get close to the
dimensions needed, but
not close enough to trust
making the cuts. They
would have to wait until
they received the equipment and then complete the project in seven days to have
the equipment back in service.
|